Grantham Roadworks Update 24/10/24: Station Approach and Dysart Road improvements pass the halfway mark

The two Grantham projects are still set to be finished this December.

Cllr Richard Davies, executive member for highways, said: “Our final two Grantham improvement schemes for 2024 are continuing ahead as planned, with both still on track to be finished ahead of Christmas this year.

“We just need the weather to cooperate with us as we head into autumn and winter, so it stays as dry as possible. We’ve had a fair bit of heavy rain over the past couple weeks which, luckily, hasn’t delayed either project. But as we get closer to the end of both schemes, we’ll need dry weather so we can lay the final layer of tarmac – which can’t be laid when it’s wet.”

“I want to thank everyone for their continued patience while both sets of work are being carried out. We’ll continue doing all we can to keep disruption to a minimum.”

Combined project facts and figures

Works completed to date

Dysart Road

Station Approach

Phase 1 – Westgate/Wharf Road traffic island and surrounds

Phase 2 – Wharf Road/Station Road traffic island and Station Road footway

Current and upcoming traffic management

The £3 million Dysart Road improvement project is being fully funded by Lincolnshire County Council.

South Kesteven District Council’s Station Approach project is being fully funded by a portion of the £4.1 million of Grantham Future High Street Fund funding awarded to the South Kesteven District Council in 2020 by the Department for Levelling Up, Housing and Communities and the Ministry of Housing, Communities & Local Government.

For more information about these and other major highways projects, visit www.lincolnshire.gov.uk/majorprojects.